Arizona power and energy: data, grid reliability and data centers

Arizona's electricity demand is setting records: Arizona Public Service (APS) customers set an all-time peak of 9,166 megawatts on Aug. 2, 2026 (APS), and Salt River Project (SRP) hit 9,072 megawatts on July 24, 2026 (SRP). Statewide retail sales rose about 12% from 2020 to 2025 (EIA).

Data centers are a growing share of that load: they contributed 7% of SRP's summer 2026 peak and are its fastest-growing customer segment (SRP), and APS forecasts its annual energy use will double by 2041 (APS). NERC rates the WECC-Southwest region, which includes all of Arizona, at normal risk for winter 2026–2027, summer 2026 and its five-year outlook (NERC).

Key data

Key electricity data for Arizona
MeasureValueNotesSource
Average retail price, all sectors (2025)12.95¢/kWhU.S. average 13.56¢. Rank 20 of 50 states + D.C. (1 = highest price)EIA Electric Power Annual, Table 2.10
Residential price (2025)15.26¢/kWhU.S. 17.23¢. Rank 28 of 51EIA Table 2.10
Commercial price (2025)12.45¢/kWhU.S. 13.37¢. Rank 22 of 51EIA Table 2.10
Industrial price (2025)8.05¢/kWhU.S. 8.51¢. Rank 32 of 51EIA Table 2.10
Total retail sales (2025)92.1 million MWhNo. 15 among the states; up 1.4% from 2024EIA Table 2.8
Change in retail sales, 2020–2025+12.4%82.0 million MWh in 2020 (EIA State Electricity Profile, Table 8) to 92.1 million MWh in 2025 (EIA Table 2.8)EIA Arizona Electricity Profile
Utility-scale net generation (2025)116.5 million MWhUp 0.4% from 2024EIA Table 3.7
Largest power plantPalo Verde (nuclear)32.4 million MWh in 2024, the state's largest plant by generationEIA Arizona Electricity Profile, Table 2B

Generation mix, 2025

Generation mix for Arizona, 2025
SourceShareThousand MWh
Natural gas45.2%52,670
Nuclear26.9%31,322
Solar (utility-scale PV and thermal)13.3%15,505
Coal7.9%9,219
Hydroelectric (incl. pumped storage)4.2%4,854
Wind2.7%3,150
Other (biomass, petroleum, net storage)-0.2%-249
Total116,471

Utility-scale facilities, all sectors, thousand megawatthours. "Other" is negative because energy storage consumes more electricity than it returns. Shares may not sum to 100% because of rounding. Small-scale (rooftop) solar, estimated at 5.8 million MWh in 2025, is not included.

Source: EIA Electric Power Annual 2025, Tables 3.7–3.22 (released Oct. 21, 2026)

Grid reliability

Arizona is in the Western Interconnection. NERC's WECC-Southwest assessment area, a summer-peaking region, includes all of Arizona and New Mexico, most of Nevada and small parts of California and Texas (NERC 2026–2027 Winter Reliability Assessment). The state's largest utilities, APS, SRP and Tucson Electric Power (TEP), each publish their own resource plans (APS; SRP; TEP).

Winter 2026–2027: normal risk. NERC finds WECC-Southwest can meet operating reserve requirements across the scenarios it assessed, including an extreme winter peak of 25,635 MW with extreme outages. Winter peak demand is forecast to rise 2.9 GW (14.6%) from last winter, but added wind and battery capacity exceeded that growth (NERC WRA).

Summer 2026: normal risk. NERC's summer assessment found WECC-Southwest had the largest year-over-year increase in net internal demand of any assessment area, +9.5%, with an anticipated reserve margin of 48.1% (NERC 2026 Summer Reliability Assessment).

Long term: normal risk through 2030. WECC-Southwest is not among the elevated- or high-risk areas in NERC's 2025 Long-Term Reliability Assessment (January 2026), which showed no loss-of-load hours or unserved energy for the area in 2027 or 2029 (NERC LTRA).

Utility planning. APS's 2026 Integrated Resource Plan, filed with the Arizona Corporation Commission, projects peak demand above 14,500 MW in 2041 (3.4% a year) and retail sales doubling to about 80,600 GWh (APS). SRP says its generation capacity is about 13,000 MW and that transmission for a new data center takes five to eight years to build (SRP).

Outage history. Arizona utilities reporting to EIA averaged 84 minutes of interruption per customer in 2024 including major events (70 minutes excluding major event days) (EIA Arizona Electricity Profile, Table 17).

Big projects and what to watch

Reference summary of public utility, grid-operator and company filings; not news coverage.

  • APS new generation

    APS's 2026 plan adds natural gas through the new Desert Sun Power Plant, an expansion of the Saguaro Power Plant and conversion of the retired coal-fired Cholla plant, and expects about 6,000 MW of battery storage by 2030 (APS). Its Redhawk expansion in Arlington adds eight gas units, up to 397 MW, by fall 2027 (APS).

  • SRP additions and data-center rules

    Since summer 2025, SRP brought the Copper Crossing solar project, Flatland and Pediment battery storage and the Coolidge Expansion Project online, nearly 800 MW combined (SRP). Large customers taking service after Nov. 1, 2025, face a 15-year minimum term, collateral and an 80% minimum demand charge (SRP).

  • TEP data-center service agreement

    The Arizona Corporation Commission approved TEP's agreement to provide up to 286 MW of 138-kV service to a planned data center southeast of Tucson on Dec. 3, 2025. TEP says it can serve it with existing resources plus solar and storage under development, including the 400 MW Roadrunner Reserve battery (TEP).

  • What to watch

    Arizona Corporation Commission review of APS's 2026 Integrated Resource Plan, SRP's integrated system planning for data-center load, and NERC's next long-term assessment of WECC-Southwest.

On the Powering America Podcast

Related coverage

Frequently asked questions

How much does electricity cost in Arizona?

The average retail price across all sectors was 12.95 cents per kilowatthour in 2025, slightly below the U.S. average of 13.56 cents. Residential customers paid 15.26 cents on average, according to EIA's Electric Power Annual (Table 2.10).

Where does Arizona get its electricity?

In 2025, natural gas produced 45.2% of Arizona's utility-scale generation, nuclear 26.9% (from the Palo Verde Generating Station), solar 13.3%, coal 7.9%, hydroelectric 4.2% and wind 2.7%, according to EIA's Electric Power Annual.

How fast is Arizona's electricity demand growing?

Statewide retail sales rose about 12% from 2020 to 2025, according to EIA. APS set a record peak of 9,166 MW on Aug. 2, 2026, and forecasts annual energy use will double by 2041; SRP set a record 9,072 MW on July 24, 2026.

How much of Arizona's power demand comes from data centers?

SRP says data centers contributed 7% of its summer 2026 peak demand and are its fastest-growing customer segment. APS and SRP both require large new customers, including data centers, to cover the costs of serving them.

Has the Powering America Podcast covered Arizona energy?

Yes. Arizona State University economist Domenico Ferraro discussed data centers and electricity demand (Sept. 15, 2026), and William Beard of the Arizona-based Goldwater Institute discussed data-center energy and water use (April 28, 2026).

Sources

  1. EIA, Electric Power Annual 2025 (data for 2025, released Oct. 21, 2026)
  2. EIA, Table 2.10: Average price of electricity by end-use sector, by state, 2025 and 2024
  3. EIA, Table 2.8: Sales of electricity to ultimate customers by state, 2025 and 2024
  4. EIA, Table 3.7: Net generation by state by sector, 2025 and 2024
  5. EIA, Arizona Electricity Profile 2024 (released Nov. 10, 2025)
  6. EIA, Arizona Electricity Profile data tables (Tables 2B, 8 and 17)
  7. NERC, Winter Reliability Assessments (2026–2027 assessment, Nov. 18, 2026)
  8. NERC, Increasing demand and El Niño challenge winter grid reliability (Nov. 18, 2026)
  9. NERC, Summer Reliability Assessments (2026 assessment, May 2026)
  10. NERC, Long-Term Reliability Assessments (2025 assessment, January 2026)
  11. APS, APS delivers reliable service through record summer demand (October 2026)
  12. APS, APS 2026 Integrated Resource Plan focused on reliability, affordability (Nov. 2, 2026)
  13. APS, Redhawk Power Plant Expansion Project
  14. SRP, SRP sets multi-day record for energy demand amid extreme heat (July 27, 2026)
  15. SRP, Data centers and SRP
  16. TEP, Data center campus proposal (energy supply agreement)

Figures are compiled from the linked public sources as of Nov. 18, 2026. Reference only.